Resource Capacity

Resource Management answers a simple question for a project manager: do the people needed for this work actually have the time? A resource plan requests capacity for a project from a resource group; resource allocations split a confirmed plan across named people; the Allocation Workbench shows both against real capacity, period by period.

State What it means Typical next action
Planning Drafted, not yet sent to the resource manager. Request (requires the resource-planner role), or Cancel
Requested Waiting on the resource manager. Confirm, Reject, or Cancel
Confirmed Quantity agreed; not yet hardened into named allocations. Allocate, or Cancel
Allocated Hardened into named-person allocations. Complete
Completed Terminal — the plan’s window has finished.
Cancelled Terminal side-exit.

Confirm requires entering a confirmed quantity and is gated behind the resource-manager role, as is Allocate and Reject (which sends a requested plan back to Planning). A plan requests its quantity in one of three units — Hours, FTE, or Person-days — all of which the workbench converts to a common hours figure internally.

An allocation splits a resource plan across a specific person with an hours figure and a date window.

State Typical next action
Planned Confirm, or Cancel
Confirmed Allocate
Allocated Terminal
Cancelled Reopen

The workbench is a Group → User tree crossed with a period grid (Week or Month buckets, toggleable), showing each cell as Planned vs. Allocated hours with a threshold color:

Tone Meaning
Unallocated Demand exists (planned > 0) but nothing is allocated yet.
Partial Some, but not all, of the planned demand is allocated.
Allocated Demand is fully covered (or work is allocated with no planned figure behind it).
Over Allocated hours exceed the person or group’s capacity for that period — flagged regardless of what was planned.

Capacity for a period is computed at read time, not stored: it’s the number of working weekdays in that period × 8 hours × the person’s FTE (default 1.0 when unset). Availability is capacity minus allocated hours. A toolbar lets you switch the display unit between Hours, FTE, and Person-days, and toggle an Availability column on or off — the underlying numbers are always stored in hours and converted for display.