Resource Capacity
Resource Management answers a simple question for a project manager: do the people needed for this work actually have the time? A resource plan requests capacity for a project from a resource group; resource allocations split a confirmed plan across named people; the Allocation Workbench shows both against real capacity, period by period.
Resource Plans
Section titled “Resource Plans”| State | What it means | Typical next action |
|---|---|---|
| Planning | Drafted, not yet sent to the resource manager. | Request (requires the resource-planner role), or Cancel |
| Requested | Waiting on the resource manager. | Confirm, Reject, or Cancel |
| Confirmed | Quantity agreed; not yet hardened into named allocations. | Allocate, or Cancel |
| Allocated | Hardened into named-person allocations. | Complete |
| Completed | Terminal — the plan’s window has finished. | — |
| Cancelled | Terminal side-exit. | — |
Confirm requires entering a confirmed quantity and is gated behind the resource-manager role, as is Allocate and Reject (which sends a requested plan back to Planning). A plan requests its quantity in one of three units — Hours, FTE, or Person-days — all of which the workbench converts to a common hours figure internally.
Resource Allocations
Section titled “Resource Allocations”An allocation splits a resource plan across a specific person with an hours figure and a date window.
| State | Typical next action |
|---|---|
| Planned | Confirm, or Cancel |
| Confirmed | Allocate |
| Allocated | Terminal |
| Cancelled | Reopen |
The Allocation Workbench
Section titled “The Allocation Workbench”The workbench is a Group → User tree crossed with a period grid (Week or Month buckets, toggleable), showing each cell as Planned vs. Allocated hours with a threshold color:
| Tone | Meaning |
|---|---|
| Unallocated | Demand exists (planned > 0) but nothing is allocated yet. |
| Partial | Some, but not all, of the planned demand is allocated. |
| Allocated | Demand is fully covered (or work is allocated with no planned figure behind it). |
| Over | Allocated hours exceed the person or group’s capacity for that period — flagged regardless of what was planned. |
Capacity for a period is computed at read time, not stored: it’s the number of working weekdays in that period × 8 hours × the person’s FTE (default 1.0 when unset). Availability is capacity minus allocated hours. A toolbar lets you switch the display unit between Hours, FTE, and Person-days, and toggle an Availability column on or off — the underlying numbers are always stored in hours and converted for display.